Progress in Marion and Pisgah Forest

Well the exterior gutters are going on today and basically wrapping up the exterior portion of the Pisgah forest Home. Meanwhile drywall is being finished on the second floor. Hope to be installing flooring in a week. The Marion home is actually farther along than shown as the stick built portion of the roof is now done and on to sheathing ready for roofing and windows /doors next week . Its good to see things happening and we are thankful this season for the people who have entrusted us with their most important investment their home.